M/s xxx Properties LLC
P.O. Box xxx, Dubai, U.A.E.
Tel: xxx
Fax: xxx
Attention : Engr. xxx
Project Manager
Project : (G+7F) xxx Apartment – Civil Works
Subject : Variations for Reception Counter – Additional Costs – Revision 1
Dear Sir,
Further to our letter reference xxx dated 17th November xxx regarding to the additional costs for reception counter and to the recent instruction from the client, thus, we are submitting herewith our claim for the additional cost amounted to AED 112,022.10 (UAE Dirham One Hundred Twelve Thousand, Twenty Two and Ten Fils Only), details as per the attached documents.
In view of the above, we request for your necessary approval in order for us to proceed further, moreover this additional work shall entitle us for extension of time for completion.
This is for your information and necessary action.
Sincerely Yours,
For Xxx(Name of the Subcontractor) Interiors LLC
xxx
Project Manager