VARIATION WORK TO xxx INTERIORS
M/s xxx Constructions and Operations
Office No,. xxx,
Financial Tower, DIFC xxx
Tel: xxx
Fax: xxx
Attention : Mr. xxx
Project Manager
Project : xxx – 6B+G100 Floors-Hotel & Residential Tower
Client : M/s xxx Holdings Ltd
Consultant : M/s xxx Architectural & Engineering Consultants)
Subject : VARIATION WORK TO xxx INTERIORS
Dear Mr. Ibrahim,
With reference to the subject and in response to your letter xxx dated 23rd December xxx, herein we request your kind attention to facilitate the subcontract addendum to cover this variation cost and considering the following payment terms:
- 25% Advance Payment against security cheque
- 65% on installation payable after 60 days from the date of our invoice submission date
- 10% Retention to be released as follows:
3.1 5% after project preliminary handing over
3.2 5% after project final handing over
In view of above, upon signing the subcontract addendum, we will be ready to comply with M/s Client’s requirement.
Kind Regards,
For xxx Interiors LLC
xxx
Project Manager