VARIATION WORK TO xxx INTERIORS

VARIATION WORK TO xxx INTERIORS

M/s xxx Constructions and Operations                            

Office No,. xxx,

Financial Tower, DIFC xxx

Tel: xxx

Fax: xxx

Attention          :   Mr. xxx

                            Project Manager                    

Project             :  xxx – 6B+G100 Floors-Hotel & Residential Tower

Client               :  M/s xxx Holdings Ltd

Consultant       :  M/s xxx Architectural & Engineering Consultants)

Subject           :  VARIATION WORK TO xxx INTERIORS

Dear Mr. Ibrahim,

With reference to the subject and in response to your letter xxx dated 23rd December xxx, herein we request your kind attention to facilitate the subcontract addendum to cover this variation cost and considering the following payment terms:

  1. 25% Advance Payment against security cheque
  2. 65% on installation payable after 60 days from the date of our invoice submission date
  3. 10% Retention to be released as follows:

3.1 5% after project preliminary handing over

3.2 5% after project final handing over

In view of above, upon signing the subcontract addendum, we will be ready to comply with M/s Clientโ€™s requirement.

Kind Regards,

For xxx Interiors LLC

xxx

Project Manager                                                                                    