Variation of Nominated Subcontractor and Main Contractor profit and overhead

Variation of Nominated Subcontractor and Main Contractor profit and overhead

Date:               xxx

Ref:                  xxx

Kind Attn         :Mr. xxx

Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai

Subject               : Variation confirmation of Nominated Subcontractor xxx and xxx for

                               Main Contractor (10% over head and profit)                                           

Dear Sir,

With reference to the above mentioned subject, we would like to inform you that   as per our terms and condition in LOI item No.5, C-2 our letter ref-CC/CITYMxxx dtd 16th June xxx (Attached) kindly note the following.

  1. xxx Contract amount AED 790,954.00 -10% over head and profit AED 79,095(Attached)
  • xxx contract amount AED 350,294.00-10% Over head and Profit AED 35,029(Attached)

So, kindly issue the variation order as per the contract so we can include in running invoice.

Regards,

For xxx Contracting L.L.C.

xxx

Project Manager