M/s xxx Building Contracting LLC
PO Box xxx, Dubai, U.A.E
T: xxx | F: xxx
Email: xxx
Attention : MR. xxx
Project Manager
Project : xxx Sky Tower – Umm Ramool
Subject: Variation No. 2 – Additional Cost
Dear Sir,
We refer to our letter reference xxx dated 28th September xxx and to your subsequent letters reference xxx dated 29th September xxx and reference xxx dated 3rd October xxx in relation to your instruction to proceed and the Consultant’s comments respectively.
Please be informed that we agree on the Consultant’s comments as follows;
- Deletion of internal drawers handles will cover the extra cost for the changing of Wardrobe handles from 200mm to 350mm length, hence, no cost implication.
- To keep the filler panel and no change will be required, hence, no cost implication.
- Vanity Unit opens shelves to change from melamine to veneer same color as door, no cost implication.
However, for the addition of Plinth Block (architrave shoe) on each face of door, the increasing of the height of the Kitchen Wall Unit and the deletion of the carcass for the Kitchen Base Unit, there will be corresponding cost implications as summarized below;
Item | Description | Unit | Qty. | Rate (AED) | Amount (AED) |
Addition: | |||||
1 | Addition of Plinth Block (architrave shoe) to doors | Nos. | 2932 | 55 | 161,260 |
2 | Changing the Wall Unit height from 800mm to 880 mm high | Nos. | 279 | 87,088 | |
Subtotal Addition | 248,348 | ||||
Omission: | |||||
3 | Omission of carcass on Kitchen Base Unit to accommodate the Washing Machine | Nos. | 260 | 95 | -24,700 |
Subtotal Omission | -24,700 | ||||
GRAND TOTAL | 223,648 | ||||
UAE Dirham Two Hundred Twenty Three Thousand Six Hundred Forty Eight Only |
We look forward in receiving your order confirmation on the above cost, and should you need additional information, please do not hesitate to contact us.
Sincerely Yours,
For Xxx (Name of the Subcontractor) Interiors LLC
xxx
Commercial Manager