Variation Order Request

Variation for additional column and block wall at main entrance area in Ground Floor.

Date:               xxx

Ref:                  xxx

Kind Attn         :Mr. xxx

Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai

Subject        : Variation for additional column and block wall at main entrance area in

Ground Floor.

Dear Sir,

With reference to above subject we would like to submit variation at entrance area in MAKSTYLO subcontractor zone which include plaster, block work, RCC column, etc.

Sr.NoDescriptionNoLBHQuantityUnit rateCostRemarks
1.Chemical tube for hole drilled in floor for 14mm dia and 15mm depth. 4 nos of steel in each column. Total nos of steel in 2 columns = 82 columns8 holes122122Minimum 1 tube required to purchase Refer to Page no. 4 for Quotation
2.Drilling of hole by making additional arrangement     Ls100 
3.RCC column2 columns0.20.2540.21200480For 1 column = 240 AED Refer to Page No. 3 for Rate and Page No. 5 for drawing. Ref: Bill No. 04/1/4, Item A
4.RCC coping beam 0.3 meter (small beam)10.30.20.20.012120014.4Refer to Page No. 3 for Rate and Page No. 5 for drawing. Ref: Bill
No. 04/1/4, Item A
5.RCC coping beam 0.6 meter (small beam)10.60.20.20.024120028.8Refer to Page No. 3 for Rate and Page No. 5 for drawing. Ref: Bill
No. 04/1/4, Item A
6.Plastering for both columns (0.55 + 0.55 + 0.2) x 4m = 5.2 sqm (0.9 + 0.9 + 0.25) x 4m = 8.2 sqm Total Area = 13.4 sqm2 columns   13.430402Painting by ID subcontractor, Refer to Page no. 5 for drawing
SUB-TOTAL1147.2 
VAT (5%)57.36 
TOTAL1204.56 

Regards,

For xxx Contracting L.L.C.

xxx

Project Manager

Leave a Comment

Your email address will not be published. Required fields are marked *

Scroll to Top