Variation against Additional Breaching Inlets and Wet Risers
Date: xxx
Ref: xxx
Kind Attn :Mr. xxx
Project: 2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai
Subject: Submission of the Positive Variation against Additional Breaching Inlets and Wet Risers
Dear Sir,
With respect to above, we are hereby submitting Variation Order#62 for the Supply and Installation of Pipes, Fittings and Accessories for the Additional Wet Risers and Breeching Inlets according to the DCD Regulation and Comments. Kindly find below listed documents enclosed with this Variation Order.
- Detailed Breakdown of the Variation Order
- BOQ Reference for Unit Price
- BOQ Breakdown
- BMTS Quotation
- Tender Drawings
- Joint Measurement Sheet
- DCD Approved Drawings
- As-built Drawings
Description | Amount |
Additional Sprinkler Riser, Landing Valve/Hose Reel Riser and Breeching Inlets according to the DCD Comments including Alteration and Modification Work | 150,065 AED |
Contractor’s Profit, Overhead and Coordination Charges (10%) | 15,006.50 AED |
Grand Total | 165,071.50 AED |
Looking forward for your kind review and approval….
Regards,
For xxx Contracting L.L.C.
xxx
Project Manager
Md Abu Zaed Khan
0
Tags :