Variation against Additional Breaching Inlets and Wet Risers

Variation against Additional Breaching Inlets and Wet Risers

Date:               xxx

Ref:                  xxx

Kind Attn         :Mr. xxx

Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai

Subject: Submission of the Positive Variation against Additional Breaching Inlets and Wet Risers

Dear Sir,

With respect to above, we are hereby submitting Variation Order#62 for the Supply and Installation of Pipes, Fittings and Accessories for the Additional Wet Risers and Breeching Inlets according to the DCD Regulation and Comments. Kindly find below listed documents enclosed with this Variation Order.

  1. Detailed Breakdown of the Variation Order
  2. BOQ Reference for Unit Price
  3. BOQ Breakdown
  4. BMTS Quotation
  5. Tender Drawings
  6. Joint Measurement Sheet
  7. DCD Approved Drawings
  8. As-built Drawings
DescriptionAmount
Additional Sprinkler Riser, Landing Valve/Hose Reel Riser and Breeching Inlets according to the DCD Comments including Alteration and Modification Work150,065 AED
Contractor’s Profit, Overhead and Coordination Charges (10%)15,006.50 AED
Grand Total165,071.50 AED

Looking forward for your kind review and approval….

Regards,

For xxx Contracting L.L.C.

xxx

Project Manager

Leave a Reply

Your email address will not be published. Required fields are marked *