Pods Delivery

TYPE “C” – Mock up Pods.

Our Ref: xxx

Date: xxx

To                    :           xxx Engineering & Contracting Co. (L.L.C.)

                                    P. O. Box xxx

            Dubai

            U.A.E.

Attention          :           Engg. xxx

Project             :           xxx Town Houses

                                    Subcontract Agreement Ref No.:xxx

Subject                                 : TYPE “C” – Mock up Pods.

Dear Mr. xxx,

Based on the approved shop drawings received on 2nd of February, we require minimum 15 days to produce the 3 ground floor pods. The mould works for the floors are already stated and these are expected to cast only on Wednesday 11th of February.

The latest delivery of the ground floor pods will be on 18th of February at site. We will do all possible to improve this date and will update you accordingly.

Hope you will understand the situation and cooperate with us.

Yours faithfully,

On behalf of xxx LLC

xxx

Projects Manager

Leave a Comment

Your email address will not be published. Required fields are marked *

Scroll to Top