Project: 2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai
Subject : Regarding toilet shop drawing for unit no 4 from 5th floor to 13th floor pending for approval.
Dear Sir,
With reference to above and our submittal reference noxxx was submitted on 30th August xxx and still approval is awaited from your office and the toilet work under hold in all respect at all floor starting from 5th floor.
Kindly release the drawing as soon as possible to allow us to complete toilet work which is pending from 5th floor to 13th floor.
This is for your kind information and request to do needful.