Date: xxx
Ref no: xxx
To
The Manager,
DM Qualification Section (License)
Dubai Municipality,
Dubai UAE
Sub : Submission of the proposal to close the distribution pump opening in PT slab from 4th floor to roof located in corridor
Dear Sir,
With reference to the above, we are hereby submitting the proposal and approval by the consultant and design confirmation by the PT subcontractor and attaching herewith the following for your reference and review.
- Consultant approval
- Method of statement
- VLM Emirates (PT subcontractor design confirmation
- DM approved drawing for temporary opening
- Design proposal for closeout with “L” angle and rebar
So, kindly review and request to close the violation
Thanks with Regards,
xxx
(Managing Director)
xxx Contracting L.L.C