Serious concern for the mock up approval due to verbal comments and delay issue.

Serious concern for the mock up approval due to verbal comments and delay issue.

Date:               xxx

Ref:                  xxx

Kind Attn         :Mr. xxx

Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai

Subject           : Regarding our serious concern for the mock up approval due to verbal comments and delay issue.

Dear Sir,

With reference to the above, we have a serious concern for the Vanity Counter inspection and note the following.

  1. Inspection raised on 27th July 2017, was released on 9th Sep 2017 with unethical statement that it was verbally  commented on 3rd Sep 2017, no such verbal instruction happen.

Kindly review your communication AP/CC/269/418 which is received on 4th Sep 17, with instruction to submit the inspection request.

  • Our ref no CC/AP/555/17 dtd 3rd Sep 2017, is replyed on 4th Sep 2017 So, no such inspection or verbal instruction happened at the site.               

We will not accept any verbal instruction without comment on the drawing and we like to inform you, we will not responsible for any delay for approval.If it is verbally instructed and further request that statement is unethical and self-explanatory as per attachment.

Regards,

For xxx Contracting L.L.C.

xxx

Project Manager

Leave a Reply

Your email address will not be published. Required fields are marked *