False ceiling work

Revised RCP

Our Ref: xxx

Date: xxx

To                    :           xxx Middle East,

                                    P.O.Box xxx,

            Dubai – UAE.

Attention          :           Mr. xxx

                        :           Project Manager

Project             :           xxx Towers Project, Dubai

Subject:                 Revised RCP

Dear Mr. Loh,

We have received today the revised Reflected Ceiling Plans under Aconex Transmittal Reference: xxx attaching Mace letter to xxx dated 14th October xxx.

  • We have looked briefly and found out that many access panels moved positions compared to the reflected ceiling plans received on 15th of September xxx and the agreed locations during the shop drawings preparation and approval thereafter.
  • Please note that such changes, even few centimeters left or right, or orientations, will force us to revise all the shop drawings.
  • Moreover, we already started manufacturing pods based on the approvals obtained so far.  A change at this point will put the whole production on hold, and will have consequences on the produced ceilings so far.

We would like to call for a conference call tomorrow around 11 a.m. to discuss this issue further and try to avoid such changes at this stage.  Our Technical & Design Manager Mr. xxx Hansen will call Mr. xxx at that time.

Yours faithfully,

On behalf of  xxx LLC

xxx

Project Manager       