Date: xxx
Ref: xxx
Kind Attn :Mr. xxx
Project: 2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai
Subject : Resubmission of Variation for the LPG Placement over the Ramp Area
(Only for Structure and Civil Works) new building permit no xxx
transmittal ref no AP/269/CC/62.
SRNO | ITEM DESCRIPTION IN NOMINATION | CONTRACT BOQ ITEM REF | QTY | UNIT | RATE | AED |
1 | Covering of Cut out for LPG placement over the ramp area between Grid 1-2/A-B with steel structure and other required work ( Only for steel structure and Civil Work) Other variation will be submitted separately | NEW SCOPE Not available in Contract Bldg. Permit No. 3731297 241570-26-1 dated 29/10/17 | 135,602.17 | 135,602.17 | ||
TOTAL AED | 135,602.17 |
( Dirham: One Hundred Thirty Five Thousand six hundred two and seventeen fills only)
Attached are herewith
- Variation at first floor ( revised).
- Proof for dimensions for various activities.
- AL KARAM METAL WORKS LLC( Supply and Installation Quotation with break down of total cost).
- M/s NASCO STEEL CONTRUCTION LLC ( Supply and Installation Quotation break down of total cost).
- AL BALAD METALS CONTRACTING LLC( Supply and Installation).
- HILTI quotation ( for chemical tubes)
NOTE : Two sub contractors have submitted macro level break up for their total cost whereas the third one has not yet submitted.
Regards,
For xxx Contracting L.L.C.
xxx
Project Manager