Response to Delay in Delivery of PODs

Response to Delay in Delivery of PODs

Our Ref: xxx

Date:

To

xxx Contracting LLC

P. O. Box xxx

Dubai, U.A.E.

Attention            : Mr. xxx, Group Procurement Manager

Project                 : xxx Phase 2

Subject                 : Response to Delay in Delivery of PODs

Dear Sir,

We refer to our letter dated 20 Aug xxx ref. xxx which remained unanswered.

Instead of reverting to our offer to finalize and agree a programme that accounts all outstanding issues (none of which attributable to us) such as the one suggested in August xxx, you have chosen to harass us with notices of delays that lack any contractual foundation.

Based on the foregoing and considering your evidenced bad faith in the execution of the Subcontract Agreement (in total disregard of your legal duties under Article 246 of the UAE Civil Code) and in it performance, and as already stated in our letter dated 20 Aug xxx ref. xxx, the Subcontract Agreement is now be deemed as repudiated by you and you shall be liable for the consequences of such repudiation.

You are invited to appoint a contact form your end for us to hand-over.

Our rights are fully reserved.

Yours faithfully,

On behalf of xxx LLC                                                                      

xxx

project Manager