Date: xxx
CC/CI/03
Kind Attn: The Manager, xxx Interior Division
Project: 2B + G + 14 + Lower Roof Hotel Building
Plot No. 373-1297 at Barsha, Dubai
Subject: Requirement of approved material submittals for partition wall -Citymax
Dear Mr. xxx,
With ref. to above we have given all the details to Mr. Raju concerned person from Interior division which include full acoustic assessment report, firefighting details, drawings related to partition wall with section details from A1-A9 and explained how to get the areas from the drawings where he must follow both the sides areas , locations and follow the partition to be done.
So, kindly confirm we are expecting the approved material submittals with all the certificates for fire rating and DCL Certificate and Sound insulation details within one week.
Regards,
For xxx Contracting L.L.C
xxx
General Manager