Date: xxx
CC/269/TC/01
To: Al Balqa Trading
Kind Attn: Mr. Mohammed Saeb
Project: 2B + G + 14 + Lower Roof Hotel Building
Plot No.: 373-1297 at Barsha, Dubai
Subject: Regarding tower crane horizontal bracing accessories at third floor
Dear Sir,
With ref. to above, we are here by informing you that we are working at the third floor slab, as per your design drawing of tower crane you need to fix the horizontal bracingaccessories prior to casting of slab for future support where the slab is in progress.
So, kindly do needful immediately, provide the required horizontal bracingaccessories by tomorrow since we are starting the PT work of the third floor slab level after which it is very difficult to disturb the PT arrangement.
Regards,
For xxx Contracting L.L.C
xxx
General Manager