Reply - Notice of Delay

Regarding our MEP subcontractor and ID subcontractor

Date:               xxx

Ref:                  xxx

Kind Attn         :Mr. xxx

Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai

Subject          : Regarding our MEP subcontractor and ID subcontractor.

Dear Sir,

With reference to the above, we are attaching herewith the Destec sub contractor mail and their requirement is self-explanatory and kindly note the following.

  1. Our MEP sub contractor required complete elevation of the kitchen and section detail for every area to coordinate  and prepare the shop drawing
  2. Our Interior sub-contractor also required the elevation and section details along with the dimension to prepare the shop drawing for ceiling.
  3. The ground floor area we required complete detail with plan elevation and section as the same requirement for our MEP sub contractor as well as interior sub-contractor will also require the same.
  4. As we discussed in the meeting there is additional block wall required by kitchen sub-contractor so, we also require the wall detail’s with elevations to check the finishes on the wall and other MEP requirement.

So, kindly provide complete detail drawing as explain above without detail drawing none of the sub contractor will not submit the shop drawing or unable to execute their work.

Regards,

For xxx Contracting L.L.C.

xxx

Project Manager