False ceiling work

Re-Notice for Remaining/Pending works for the Project

Our Ref: xxx

Date: xxx

To                    :           xxx Mideast

                                   Oman Branch

Attention          :           Mr. xxx Sing

Project             :           xxx Building, Oman

Subject                 : Re-Notice for Remaining/Pending works for the Project

Reference:         a) Xxx letter xxx dated 24 August xxx

b) Xxx letter xxx dated 21 January xxx

                                c) Xxx letter xxx dated 21 April xxx

                                d)  Xxx letter xxx dated 22 April xxx

                                e) Xxx letter xxx dated 21 June xxx

f) Xxx letter xxx dated 26 July xxx

g) Xxx letter xxx dated 30 August xxx

h) Xxx letter xxx dated 31 August xxx

i) Xxx letter xxx dated 01 September xxx

j) Xxx letter xxx dated 09 September xxx

Dear Sir,

We are writing in response to letter ref: xxx received on 13 September xxx and we note that the letter is addressed to all the Subcontractors and not to Xxx specifically. Nevertheless, we must record the following:

We refer to our previous letters referenced above, mainly letters (h), (i) & (j) and note once again that there is no remaining/pending works related to Xxx.

The close out documents related to our scope are submitted, all the works related to us are completed and no any action is pending on Xxx.

Once O&M is approved & TOC is obtained, Original warranties will be arranged accordingly.

In the end, we remind you on the amount of OMR xxx overdue since almost a year and a half and we urge you to release it on immediate basis.

Thanks,

On behalf of Xxx LLC

xxx

Project Manager