Re- FIP POD Inspection Comments from the Engineer

Re- FIP POD Inspection Comments from the Engineer

Our Ref: xxx

Date:

To

xxx Contracting LLC

P. O. Box xxx

Dubai, U.A.E.

Attention            : Mr. xxx, Group Procurement Manager

Project                 : xxx Phase 2

Subject:                Re- FIP POD Inspection Comments from the Engineer

Dear Sir,

We are in receipt of your letter No. xxx dated 15 August xxx regarding the Engineer’s comment to the First in Place POD type 1 inspected on 10 August xxx at M/s xxx (Contractor Name) factory.

Kindly find below our point wise response to each of the comments.

SN ENGINEER COMMENTM/s xxx (Contractor Name) RESPONSE
1All gypsum wall grid corners to be completely closed and well tiedWall grids corners are well tied. However, the profiles are curved which will always result in slight gaps that have no impact at all, and it is not possible to have it fully closed.
2Tile grout workmanship to be improvedNoted.
3Silicon thickness surround the wash basin to be reduced as we can and workmanship to be improvedNoted and it will be reduced to the maximum possible extent. However, it is necessary to note that the washbasin does not come completely straight which will result in various gaps sizes. This is what will guide the thickness of silicone.
4Floor grouting to be replaced with epoxy grout and workmanship to be improvedNoted and replaced.
5Corner interfacing between glass partition SS channel and ceramic tiles to be improvedNoted and improved.
6Vanity counter bottom to be covered with MR gypsum board or marine plywood.Noted and applied.
7All MEP penetration to be properly sealedNotedand applied.
8Shower glass SS channel edge to be extended to cover the glass edgeNoted and end cap is installed.
9Sealant and grout workmanship to be improvedNoted and improved to the maximum possible extent.
10Access panel at the shower to be centered between glass partition and wall tileNoted. This is a design change that will be applied on all the next PODs. It cannot be applied on the First in Place as clarified during the inspection.
11Angle valve cover gap with wall to be rectifiedNoted and rectified.
12All MEP penetration to be properly sealed and vanity counter bottom to be coveredRefer to points 6 & 7 above.
13All gaps with sanitary ware to be sealedNoted.
14Improper termination of the power wiresNoted. The current termination on the pods with caps is for cable end protection only but will improve on next remaining pods to be produced.
15Concrete base to be casted with no jointsThe concrete base is casted with no joints already. The concrete base was casted monolithically with the embedded angular bar. The line showing in the pod base is normal due to 2 different materials which is the embedded angular bar and the concrete mixtures.
16Improper cutting of the vanity counter supporting channelsNoted and will be improved to the possible extent in next pods.
17All electrical conduits to be medium duty as per the approved material NO flexible conduits to be usedInstallation followed approved shop drawings. Appendix A. While flexible conduits serve better for maintenance purposes, the comment received by the Engineer is noted and flexible conduits are replaced with rigid medium duty conduits except a small portion where flexible conduits remain required to allow the minimum flexibility during any future maintenance. Refer to Appendix B for our proposal and kindly let us know if we can move forward accordingly or even such small portion of flexible conduit is not allowed.
18Floor tile grout to be replaced with epoxy grout subject to the approved material and workmanship to be improvedNoted. Refer to points 2 & 4 above.
19SS angle width to be increased to cover the back side of the edgeNoted. The tile edge is covered. Slight appearance of applied sealant on the other side will remain visible but tile edge is covered.
20Downlight location to be shifted above the wash basin and lux calculation to be submittedNoted. Lux calculation is submitted and approved. Accordingly, the downlight location was shifted and the same will be followed for all the remaining PODS.
21Hand shower base to be properly fixed to the wallNoted.

We would like to inform you that the changes and comments above are all addressed on the first in place POD (Refer Appendix C) and the POD is ready except the two points below.

  • Point no. 10 regarding the access panel that cannot be modified on the current POD and the same was explained during the inspection and agreed with the Engineer.
  • Point no. 17 regarding the flexible conduits omission and we look forward to receive your confirmation of the revised layout attached herewith as Appendix B.

Yours faithfully,

On behalf of xxx LLC                                                                      

xxx

project Manager