Date: xxx
Ref: xxx
Kind Attn :Mr. xxx
Project: 2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai
Sub : Regarding provide the approved sample of the carpet and with thickness of inlay.
Dear Sir,
With reference to above, the floor carpet is under PC rate we want to confirm the total thickness/physical sample including inlay thickness to keep margin in floor screed to review the carpet or kindly confirm in the writing to us to keep the margin for the carpet on top of the floor screed including inlay if required.
So, this information must be issue with concrete decision from the carpet supplier immediately so that we can start the screed at site.
Regards,
For xxx Contracting L.L.C.
xxx
Project Manager