Pending Works for Wardrobes

Pending Works for Wardrobes

M/s xxx Constructions and Operations                            

Office No,. xxx,

Financial Tower, DIFC xxx

Tel: xxx

Fax: xxx

Attention          :   Mr. xxx

                            Project Manager                    

Project             :  xxx – 6B+G100 Floors-Hotel & Residential Tower

Client               :  M/s xxx Holdings Ltd

Consultant       :  M/s xxx Architectural & Engineering Consultants)

Subject            :  Pending Works for Wardrobes

Dear Mr. Ibrahim,

We are in receipt of your letter reference xxx dated 6th June xxx regarding your instruction to complete the alleged pending works for the wardrobes, namely;

  • Shoe racks inside the wardrobes
  • LED lights inside the wardrobes

Please be informed that the above referred pending works are not included in our scope of works and it should be done by others, hence, these items are not considered pending from our side (please refer to the attached approved shop drawings for easy reference).

This is for your information and necessary action.

Kind Regards,

For xxx Interiors LLC

xxx

Project Manager                                                                                    