Notification of Claim No. 2

Notification of Claim No. 2

M/s xxx Building Contracting LLC       

PO Box xxx, Dubai, U.A.E

T: xxx | F: xxx

Email: xxx

Attention        :   MR. xxx

    Project Manager

 Project         :   xxx Sky Tower – Umm Ramool

Subject:            Notification of Claim No. 2

Dear Sir,

We refer to the yesterday meeting at Site Office and to the comments made on our executed mock-up where the following has been requested from Xxx (Name of the Subcontractor) Interiors;

  • All doors architrave shall be provided with the architrave shoe
  • Wardrobe handles to be changed from 200mm length to 350mm length
  • Kitchen Wall Unit height to be increased from 800mm to 880mm high
  • Kitchen Base Unit Filler panel to be replaced with cabinet shutter.
  • Vanity Unit open shelves to change the finish from melamine to veneer same color as the door.

Please be informed that the above comments on our mock-up will constitute a variation to our contract, hence, this letter will serve as our Notice of Claim for additional cost, and all the relevant details will be submitted in due course.

This is for your information and necessary action.

Sincerely Yours,

For Xxx (Name of the Subcontractor) Interiors LLC

xxx

Commercial Manager