Notice of Delay – Site Readiness

Notice of Delay – Site Readiness

M/s xxx Building Contracting LLC       

PO Box xxx, Dubai, U.A.E

T: xxx | F: xxx

Email: xxx

Attention        :   MR. xxx

    Project Manager

 Project         :   xxx Sky Tower – Umm Ramool

Subject:            Notice of Delay – Site Readiness

Dear Sir,

With regards to the above mentioned subject, we would like to notify you that till-date we are unable to take site measurements to start the production of joinery items (site photos attached to this letter for your reference) which will have an impact on our program of works.

Moreover, this is to remind you that we require 30 days after taking the site measurement to deliver the first batch of joinery items at site, hence, we request M/s xxx to expedite the site works and facilitate us in taking site measurements in order to commence the production of joinery items to avoid any further delay.

In view of the above, we reserve our rights to claim for extension of time and its associated cost which shall be provided in due course.

This is for your kind information, record and necessary action.

Sincerely Yours,

For Xxx (Name of the Subcontractor) Interiors LLC

xxx

Commercial Manager

Leave a Reply

Your email address will not be published. Required fields are marked *