advance payment

Notice of delay #2 in releasing Advance Payment

Our Ref: xxx

Date:

To

xxx Contracting LLC

P. O. Box xxx

Dubai, U.A.E.

Attention            : Mr. xxx, Group Procurement Manager

Project                 : xxx Phase 2

Subject                 : Notice of delay #2 in releasing Advance Payment

Dear Sir,

This is to notify you that you are in default of your obligation under our Subcontract Order ref: xxx clause 2.2(a) advance payment.

We have been following up on a regular basis with BGC for more that one month on the release of our advance payment without any reasonable reply, while at the same time we have been diligently performing our obligations under our Subcontract.

In accordance with the Subcontract, “the Contractor shall issue an Advance Payment 14 days after receiving a Statement and after the Contractor receives

  • The Performance Security  
  • An acceptable Guarantee in amounts and currencies equal to the Advance Payment.”

Both the Performance Security and the Advance Guarantee were received by your office on 21st October xxxx however our Advance Payment remains unsettled till this day.

Your delay in releasing the advance payment is now 33 days.

M/s xxx (Contractor Name) has so far fully funded the project and we have completed fabrication and delivery of the complete scope without having received any payment from BGC. This has severely impacted our cash flow and substantially affected our supply chain and our production process. You are therefore requested to immediately release overdue payments to avoid further disruptions.

In addition, we reserve our rights under the Terms of our Subcontract Order for an Extension of Time (EOT) equivalent to the same

Yours faithfully,

On behalf of xxx LLC                                                                      

xxx

project Manager

Leave a Comment

Your email address will not be published. Required fields are marked *

Scroll to Top