MONTHLY PROGRESS REPORT NO. 13
Month Ending 30th of September 2016
Project No : xxx
Project Title : 2B+GF+14 Floors+ Lower Roof Hotel Building
Client : xxx
Consultant : xxxx Consulting Architechs & Engineers
Contractor : xxx Contracting L.L.C.
Table of Contents:
Executive Summary…………………………………………………………………Section 1
Progress Report………………………………………………………………………Section 2
List of Equipment…………………………………………………………………. ..Section 3
Record of Manpower…………………………………………………………………Section 4
Requirement of Subcontractors / Suppliers …………………………………………Section 5
Material Submittal Log………………………………………………………………Section 6
Shop Drawing Submittal Log………………………………………………………. Section 7
RFI Log………………………………………………………………………………Section 8
Inspection Request Report Log………………………………………………….….Section 9
Method Statement Log………….…………………………………………………..Section 10
Procurement Log-Long Lead Items………………………………………………… Section 11
- Procurement Log PC Items
- Procurement Log PS Items
- Procurement Log on Long Lead Item
Progress Photos……………………………………………………………………. Section 12
HSE Report………………………………………………………………………… Section 13
Section 1
EXECUTIVE SUMMARY
- Executive Summary
Project Name : 2B + GF + 14 Floors + Lower Roof Hotel Building
Project Location : Plot No. xxx Al Barsha Dubai, UAE
Client : xxx
Lead Consultant : xxx Consulting Architects & Engineers
Project Value : AED: 33,000,000.00
Commencement Date : 09th September 2015
Project Finish : 08th January 2017
Project Duration : 488 days including mobilization
Built up Area : 1,025 m²
Project Information:
The scope of works for the 2B + GF + 14 Floors + Lower Roof Hotel Building consist of the following site works;
- Substructure foundation, reinforced in –situ concrete frame comprising ground floor plus floors, with roof level and services blocks.
- Internal and external finishes inclusive of waterproofing, insulation, supply and installation of doors and windows and all equipment and facilities identified in the Contract documents.
- The installation of Electro Mechanical Works inclusive of testing and commissioning
- External Works finishing as per specification & Drawings
Overall Progress
Mobilization : 100%
Contract duration : 488 days
Time elapsed : 386 days – 79.09%
Time left : 102 days – 20.99 %
Location of plot : Plot No. 373-1297 Al Barsha Dubai
Plot Area : 1025 m²
Total GFA : 550 m²
Section 2
PROGRESS REPORT
PROGRESS REPORT
AREA | ACTIVITY | COMPLETED |
GROUND FLOOR TO FIRST FLOOR | Reinforcement & Shutter for Columns | 100% |
Reinforcement & Shutter for RC Walls | 100% | |
Reinforcement & Shutter for Retaining Walls | 100% | |
Pouring of Concrete for Columns | 100% | |
Pouring of Concrete for Retaining Wall | 100% | |
Pouring of Concrete for RC Walls | 100% | |
First Floor PT Slab & Beam Shuttering | 100% | |
First Floor PT Slab & Beam Reinforcement | 100% | |
Casting of First Floor PT Slab & Beam | 100% |
AREA | ACTIVITY | COMPLETED |
FIRST FLOOR TO SECOND FLOOR | Reinforcement & Shutter for Columns | 100% |
Reinforcement & Shutter for RC Walls | 100% | |
Reinforcement & Shutter for Retaining Walls | 100% | |
Pouring of Concrete for Columns | 100% | |
Pouring of Concrete for Retaining Wall | 100% | |
Pouring of Concrete for RC Walls | 100% | |
Second Floor PT Slab & Beam Shuttering | 95% | |
Second Floor PT Slab & Beam Reinforcement | 95% | |
Casting of Second Floor PT Slab & Beam | 100% |
AREA | ACTIVITY | COMPLETED |
SECOND FLOOR TO THIRD FLOOR | Reinforcement & Shutter for Columns | 100% |
Reinforcement & Shutter for RC Walls | 100% | |
Pouring of Concrete for Columns | 100% | |
Pouring of Concrete for RC Walls | 100% | |
Third Floor PT Slab & Beam Shuttering | 100% | |
Third Floor PT Slab & Beam Reinforcement | 100% | |
Casting of Third Floor PT Slab & Beam | 100% | |
AREA | ACTIVITY | COMPLETED |
THIRD FLOOR TO FOURTH FLOOR | Reinforcement & Shutter for Columns | 100% |
Reinforcement & Shutter for RC Walls | 100% | |
Pouring of Concrete for Columns | 100% | |
Pouring of Concrete for RC Walls | 100% | |
Fourth Floor PT Slab & Beam Shuttering | 100% | |
Fourth Floor PT Slab & Beam Reinforcement | 100% | |
Casting of Fourth Floor PT Slab & Beam | 100% |
Section 3
LIST OF EQUIPMENT
III. LIST OF MACHINERY/EQUIPMENT AT SITE
- 14 Seater bus : 1 No.
- Generator : 2 No.
- Hand Cutter : 1 No.
- Level Machine : 2 No.
- Wood Cutting Machine : 1 No.
- Water Tank : 2 Nos.
- Mobile Crane : 1 No.
- Bending Machine : 1 No.
- Total Station : 1 No.
- Tower Crane : 1 No.
- Steel Cutting Machine : 1 No.
Section 4
RECORD OF MANPOWER
RECORD OF MANPOWER AT SITE FROM SEPTEMBER 1–SEPTEMBER 30 YEAR 2016
Month | Date | Shuttering Carpenter | Steel Fitter | Helper | Mason | Electrician | Machine Operator | Rigger | Foreman | Plumber | Painter | |
September | 1 | 11 | 22 | 5 | 3 | 2 | 1 | 1 | 1 | 3 | 2 | |
September | 3 | 17 | 25 | 8 | 7 | 3 | 1 | 1 | 1 | 3 | 4 | |
September | 4 | 16 | 23 | 8 | 5 | 4 | 1 | 1 | 1 | 2 | 4 | |
September | 5 | 16 | 25 | 7 | 6 | 4 | 1 | 1 | 1 | 3 | 3 | |
September | 6 | 13 | 23 | 7 | 3 | 4 | 1 | 1 | 1 | 3 | 4 | |
September | 7 | 15 | 22 | 7 | 4 | 3 | 1 | 1 | 1 | 3 | 4 | |
September | 8 | 13 | 22 | 7 | 5 | 3 | 1 | 1 | 1 | 3 | 4 | |
September | 10 | 18 | 20 | 10 | 5 | 5 | 1 | 1 | 1 | 3 | 4 | |
September | 11 | 18 | 24 | 14 | 10 | 3 | 1 | 1 | 1 | 9 | 6 | |
September | 13 | 12 | 17 | 17 | 4 | 2 | 1 | 1 | 1 | 6 | 4 | |
September | 14 | 15 | 22 | 13 | 5 | 4 | 1 | 1 | 1 | 5 | 5 | |
September | 15 | 16 | 25 | 5 | 5 | 3 | 1 | 1 | 1 | 4 | 5 | |
September | 17 | 14 | 15 | 10 | 5 | 5 | 1 | 1 | 1 | 5 | 5 |
Month | Date | Shuttering Carpenter | Steel Fitter | Helper | Mason | Electrician | Machine Operator | Rigger | Foreman | Plumber | Painter | |
September | 18 | 16 | 20 | 9 | 5 | 3 | 1 | 1 | 1 | 5 | 5 | |
September | 19 | 14 | 23 | 9 | 5 | 4 | 1 | 1 | 1 | 2 | 4 | |
September | 20 | 16 | 23 | 9 | 5 | 4 | 1 | 1 | 1 | 2 | 2 | |
September | 21 | 16 | 21 | 5 | 3 | 4 | 1 | 1 | 1 | 3 | 2 | |
September | 22 | 15 | 17 | 7 | 4 | 5 | 1 | 1 | 1 | 3 | 2 | |
September | 24 | 17 | 17 | 5 | 2 | 5 | 1 | 1 | 1 | 3 | 2 | |
September | 25 | 16 | 20 | 8 | 4 | 4 | 1 | 1 | 1 | 3 | 3 | |
September | 26 | 17 | 22 | 6 | 4 | 6 | 1 | 1 | 1 | 5 | 3 | |
September | 27 | 11 | 19 | 5 | 3 | 3 | 1 | 1 | 1 | 4 | 3 | |
September | 28 | 15 | 21 | 9 | 3 | 5 | 1 | 1 | 1 | 5 | 3 | |
September | 29 | 16 | 22 | 7 | 4 | 4 | 1 | 1 | 1 | 5 | 3 |
Section 5
REQUIREMENT OF
SUBCONTRACTORS / SUPPLIERS
V. Requirement of Subcontractors / Suppliers
- Plumbing
- Electrical
- HVAC
- Fire fighting
- Garbage Chute
- Elevator
- Sliding Automatic Doors
- Landscaping
- Sanitary wares and fixtures
- Gate Barriers system
- Signage
- Block work
- Plaster
- Water proofing wet areas
- Tiles
- Marble / Granite
- Interlock
- Epoxy
- Aluminum Glass & Cladding
- Paint
- Suspended Ceiling
- Metal Works
- Roof Water proofing
- Door / Joinery / Wood Works / louvers
- Glass & Mirrors
- Locks and Archive Cabinets
- Vanity Counter
- Bathroom Partitions
Section 6
MATERIAL SUBMITTAL LOG
Section 7
SHOP DRAWING SUBMITTAL LOG
Section 8
RFI LOG
Section 9
INSPECTION REQUEST REPORT LOG
Section 10
METHOD STATEMENT LOG
Section 11
PROCUREMENT LOG-LONG LEAD ITEMS
- Procurement Log PC Items
PROCUREMENT LOG PC ITEMS | |
- Granite Tile
- Ceramic Tile
- Mosaic Tile
- Internal Painting
5. Precast Wheel Stoppers
6. False Ceiling
7. Vanity Counter
8. Wardrobes
Section 11
PROCUREMENT LOG-LONG LEAD ITEMS
b. Procurement Log PS Items
PROCUREMENT LOG PS ITEMS | |
- Lift/Elevators and Dumb Waiter
- Aluminum and Glazing Works
- Joineries and Wooden Works
- Swimming Pool Including Finishes Accessories
- MEP and Equipment
- Façade Signage and Internal Signage
- Window Cleaning Equipment
- Kitchen / Deep Freezer Equipments / Cabinets
- Health Club Equipment’s
10. CCTV System and Card Access System
11. Supply of Sanitary Fitting and System
12. Ironmongries and Electronic Door Lock
13. ID Works
MEP:
- Supply of Chillers
- Supply of BMS System
- Chiller Management System
Section 11
PROCUREMENT LOG-LONG LEAD ITEMS
c. Procurement Log on Long Lead Items
PROCUREMENT LOG ON LONG LEAD ITEMS |
- Fire Pipe
- Fire Pump
- Interior Design Material
- Manhole
- Drainage Pump
- Fire Fighting System
- Calorifier
- Booster Transfer Pump
- Valves
- Auto Control Valve
- Fire and Smoke Damper
- Variable Air Volume
- Control Valves
- Chilled Water Pump
- Pressurization Unit
- IV Panel
- ATS Panel
- Busbar Riser
- BMS System
- Central Battery
- Fan Coil Units
- Exhaust and Ventilation Fan
- Ahu/fahus
- Chiller
- Generator
Section 12
PROGRESS PHOTOS
Section 13
HSE REPORT
VII. HSE REPORT
As per the safety plan submitted we are started implementations of safety plan at site as the following:
- Site workers/staff Safety Induction are done and Monthly/weekly safety reports/TBT Attached.
- Fire extinguishers 12 sets delivered at site and installed at various locations.
- Safety Mandatory and Safety Statistics board has installed at entrance gate and another safety precautions board has installed all over the site.
- Helmets, safety shoes and uniforms are made completion to all staff members and workers at site.
- First aid box has installed at site offices.
- All the safety signage has installed.
- Excavated area has been protected by safety accessories and installed deep excavation board.