MONTHLY PROGRESS REPORT

MONTHLY PROGRESS REPORT

                                      MONTHLY PROGRESS REPORT NO. 13

                                                     Month Ending 30th of September 2016

                Project No                   :         xxx

                Project Title                :         2B+GF+14 Floors+ Lower Roof Hotel Building

                Client                          :         xxx

                                      Consultant                   :         xxxx Consulting Architechs & Engineers

                                      Contractor                  :         xxx Contracting L.L.C.

Table of Contents:

Executive Summary…………………………………………………………………Section 1

Progress Report………………………………………………………………………Section 2

List of Equipment………………………………………………………………….            ..Section 3

Record of Manpower…………………………………………………………………Section 4

Requirement of Subcontractors / Suppliers …………………………………………Section 5

Material Submittal Log………………………………………………………………Section 6

Shop Drawing Submittal Log………………………………………………………. Section 7

RFI Log………………………………………………………………………………Section 8

Inspection Request Report Log………………………………………………….….Section 9

Method Statement Log………….…………………………………………………..Section 10

Procurement Log-Long Lead Items………………………………………………… Section 11

  1. Procurement Log PC Items
  2. Procurement Log PS Items
  3. Procurement Log on Long Lead Item

Progress Photos…………………………………………………………………….            Section 12

HSE Report…………………………………………………………………………            Section 13

Section 1

EXECUTIVE SUMMARY

  1. Executive Summary

Project Name                   :           2B + GF + 14 Floors + Lower Roof Hotel Building   

Project Location             :           Plot No. xxx Al Barsha Dubai, UAE

Client                               :           xxx

Lead Consultant             :           xxx Consulting Architects & Engineers

Project Value                   :           AED: 33,000,000.00

Commencement Date     :           09th September 2015

Project Finish                  :           08th January 2017

Project Duration             :           488 days including mobilization

Built up Area                   :           1,025 m²

Project Information:

The scope of works for the 2B + GF + 14 Floors + Lower Roof Hotel Building consist of the following site works;

  1. Substructure foundation, reinforced in –situ concrete frame comprising ground floor plus floors, with roof level and services blocks.
  1. Internal and external finishes inclusive of waterproofing, insulation, supply and installation of doors and windows and all equipment and facilities identified in the Contract documents.
  1. The installation of Electro Mechanical Works inclusive of testing and commissioning
  1. External Works finishing as per specification & Drawings

Overall Progress

Mobilization                           :           100%

Contract duration                    :           488 days

Time elapsed                          :           386 days   –   79.09%

Time left                                 :           102 days   –   20.99 %

Location of plot                      :           Plot No. 373-1297 Al Barsha Dubai

Plot Area                                 :           1025 m²

Total GFA                               :           550 m²

Section 2

PROGRESS REPORT

PROGRESS REPORT

AREAACTIVITYCOMPLETED
GROUND FLOOR TO                    FIRST FLOORReinforcement & Shutter  for Columns100%
Reinforcement & Shutter for RC Walls100%
Reinforcement & Shutter for Retaining Walls100%
Pouring of Concrete for Columns100%
Pouring of Concrete for Retaining Wall100%
Pouring of Concrete for RC Walls100%
First Floor PT Slab & Beam Shuttering100%
First Floor PT Slab & Beam Reinforcement100%
Casting of First Floor PT Slab & Beam100%
AREAACTIVITYCOMPLETED
FIRST FLOOR      TO               SECOND FLOORReinforcement & Shutter  for Columns100%
Reinforcement & Shutter for RC Walls100%
Reinforcement & Shutter for Retaining Walls100%
Pouring of Concrete for Columns100%
Pouring of Concrete for Retaining Wall100%
Pouring of Concrete for RC Walls100%
Second Floor PT Slab & Beam Shuttering95%
Second Floor PT Slab & Beam Reinforcement95%
Casting of Second Floor PT Slab & Beam100%
AREAACTIVITYCOMPLETED
SECOND FLOOR      TO  THIRD  FLOORReinforcement & Shutter  for Columns100%
Reinforcement & Shutter for RC Walls100%
Pouring of Concrete for Columns100%
Pouring of Concrete for RC Walls100%
Third Floor PT Slab & Beam Shuttering100%
Third Floor PT Slab & Beam Reinforcement100%
Casting of Third Floor PT Slab & Beam100%
 
                       
AREAACTIVITYCOMPLETED
THIRD FLOOR      TO  FOURTH  FLOORReinforcement & Shutter for Columns100%
Reinforcement & Shutter for RC Walls100%
Pouring of Concrete for Columns100%
Pouring of Concrete for RC Walls100%
Fourth Floor PT Slab & Beam Shuttering100%
Fourth Floor PT Slab & Beam Reinforcement100%
Casting of Fourth Floor PT Slab & Beam100%

Section 3

LIST OF EQUIPMENT

III. LIST OF MACHINERY/EQUIPMENT AT SITE

  1. 14 Seater bus                  :       1 No.
  2. Generator                               :       2 No.
  3. Hand Cutter                    :       1 No.
  4. Level Machine                :       2 No.
  5. Wood Cutting Machine  :       1 No.
  6.  Water Tank                   :       2 Nos.
  7. Mobile Crane                  :      1 No.
  8. Bending Machine           :       1 No.
  9. Total Station                   :       1 No.
  10. Tower Crane                 :       1 No.
  11. Steel Cutting Machine  :       1 No.

Section 4

RECORD OF MANPOWER

RECORD OF MANPOWER AT SITE FROM SEPTEMBER 1–SEPTEMBER 30 YEAR 2016

MonthDateShuttering CarpenterSteel FitterHelperMasonElectricianMachine OperatorRiggerForemanPlumberPainter
September1112253211132
September3172587311134
September4162385411124
September5162576411133
September6132373411134
September7152274311134
September8132275311134
September101820105511134
September1118241410311196
September131217174211164
September141522135411155
September15162555311145
September171415105511155
MonthDateShuttering CarpenterSteel FitterHelperMasonElectricianMachine OperatorRiggerForemanPlumberPainter
September18162095311155
September19142395411124
September20162395411122
September21162153411132
September22151774511132
September24171752511132
September25162084411133
September26172264611153
September27111953311143
September28152193511153
September29162274411153
 
 

Section 5

REQUIREMENT OF

SUBCONTRACTORS / SUPPLIERS

V. Requirement of Subcontractors / Suppliers

  1. Plumbing
  2. Electrical
  3. HVAC
  4. Fire fighting
  5. Garbage Chute
  6. Elevator
  7. Sliding Automatic Doors
  8. Landscaping
  9. Sanitary wares and fixtures
  10. Gate Barriers system
  11. Signage
  12. Block work
  13. Plaster
  14. Water proofing wet areas
  1. Tiles
  2. Marble / Granite
  3. Interlock
  4. Epoxy
  5. Aluminum Glass & Cladding
  6. Paint
  7. Suspended Ceiling
  8. Metal Works
  9. Roof Water proofing
  10. Door / Joinery / Wood Works / louvers
  11. Glass & Mirrors
  12. Locks and Archive Cabinets
  13. Vanity Counter
  14. Bathroom Partitions

Section 6

MATERIAL SUBMITTAL LOG

Section 7

SHOP DRAWING SUBMITTAL LOG

Section 8

RFI LOG

Section 9

INSPECTION REQUEST REPORT LOG

Section 10

METHOD STATEMENT LOG

Section 11

PROCUREMENT LOG-LONG LEAD ITEMS

  1. Procurement Log PC Items
PROCUREMENT LOG PC ITEMS
 
  1. Granite Tile
  2. Ceramic Tile
  3. Mosaic Tile
  4. Internal Painting

5. Precast Wheel Stoppers

6. False Ceiling

7. Vanity Counter

8. Wardrobes

Section 11

PROCUREMENT LOG-LONG LEAD ITEMS

b.   Procurement Log PS Items

PROCUREMENT LOG PS ITEMS
 
  1. Lift/Elevators and Dumb Waiter
  2. Aluminum and Glazing Works
  3. Joineries and Wooden Works
  4. Swimming Pool Including Finishes Accessories
  5. MEP and Equipment
  6. Façade Signage and Internal Signage
  7. Window Cleaning Equipment
  8. Kitchen / Deep Freezer Equipments / Cabinets
  9. Health Club Equipment’s

10. CCTV System and Card Access System

11. Supply of Sanitary Fitting and System

12. Ironmongries and Electronic Door Lock

13. ID Works

MEP:

  1. Supply of Chillers
  2. Supply of BMS System
  3. Chiller Management System

Section 11

PROCUREMENT LOG-LONG LEAD ITEMS

c.   Procurement Log on Long Lead Items

PROCUREMENT LOG ON LONG LEAD ITEMS
  1.   Fire Pipe
  2.   Fire Pump
  3.   Interior Design Material
  4.   Manhole
  5.    Drainage Pump
  6.    Fire Fighting System
  7.    Calorifier
  8.    Booster Transfer Pump
  9.    Valves
  10. Auto Control Valve
  11. Fire and Smoke Damper
  12. Variable Air Volume
  13. Control Valves
  1. Chilled Water Pump
  2. Pressurization Unit
  3. IV Panel
  4. ATS Panel
  5. Busbar Riser
  6. BMS System
  7. Central Battery
  8. Fan Coil Units
  9. Exhaust and Ventilation Fan
  10. Ahu/fahus
  11. Chiller
  12. Generator

Section 12

PROGRESS PHOTOS

Section 13

HSE REPORT

VII. HSE REPORT

 As per the safety plan submitted we are started implementations of safety plan at site  as the following:

  1. Site workers/staff Safety Induction are done and Monthly/weekly safety reports/TBT Attached.
  2. Fire extinguishers 12 sets delivered at site and installed at various locations.
  • Safety Mandatory and Safety Statistics board has installed at entrance gate and another safety precautions board has installed all over the site.
  • Helmets, safety shoes and uniforms are made completion to all staff members and workers at site.
  • First aid box has installed at site offices.
  • All the safety signage has installed.
  • Excavated area has been protected by safety accessories and installed deep excavation board.