Modification for Drainage Pipes in Towers 9, 10 & 11

Modification for Drainage Pipes in Towers 9, 10 & 11

Our Ref: MAAD/UP-1475/LET-0391-16/JH-sv

March 14, 2016.

To                    :           XXX International Company

            P. O. Box XXX

            Riyadh XX

            KSA.

            Tel: XX

Attention          :           Eng. XXX

                                    Email : XXX

Project             :           XXX Towers, Makkah

Subject            :           Modification for Drainage Pipes in Towers 9, 10 & 11

Dear Eng. xxx,

We would like to inform you that we are going to start the casting of our base for the pods in towers 9, 10 and 11. So Referring to our letter Ref: xxx dated 26th October xxx, we need a confirmation whether you require the modification work requested earlier in these towers.

Attached the drawings for both the options for your review and approval.

  • Type 1 Pod – Drainage Drop Down     –  As ongoing in 6, 7, 8, 12, 13 and 14 towers
  • Type 1 Pod – Drainage Horizontal out –  9, 10 and 11 towers only
  • Type 2 Pod – Drainage Drop Down     –  As ongoing in 6, 7, 8, 12, 13 and 14 towers
  • Type 2 Pod – Drainage Horizontal out –  9, 10 and 11 towers only
  • Type 3 Pod – Drainage Drop Down     –  This will remain same in all towers

                                                                (No changes is applicable)

We have received information for building 9, 10 and 11 via email. We will start counting pods for these buildings and send you the superimposed for your understanding.     

Yours faithfully,

On behalf of xxx LLC

xxx

Technical & Design Manager

Leave a Reply

Your email address will not be published. Required fields are marked *