Snagging and De-snagging

Mock Up Inspection

XXX PROPERTY INVESTMENT                                         

P.O Box xxx Dubai, UAE

Tel: xxx

Fax: xxx

Attention    :   Mr. xxx – Project  Coordinator

                      Mr. xxx – Project Coordinator                                          

Project      :  xxx Tower Apartment Project

Client         :  Mr. xxx

Subject      :   Mock Up Inspection

Dear Sirs,

Referring to the Technical Meeting we had with the Designer on 26th of March xxx please, note the following points:

  1. The Designer had given an instruction that the glass paint and the metal color in TV units including headboard should match the original fabric.  However, the metal color and glass paint cannot match according to the required fabric color.
  2. On 13th of April, a soft inspection with the Designer was held and she had noticed the difficulty of matching the color of the fabric, hence she decided to match the color in the perspective 2R picture.
  3. Accordingly, we rectified the glass again and some metals to be as per the color specified by the Designer that will lead us to modify the units and assign a new date of inspection.
  4. Furthermore, she changed the cut out of the socket area in the headboard supported with sketches on 16th of April (see attached file).  As a result, we revised the shop drawing and sent for approval again on 20th of April.
  5. Also, we revised the drawing of production and will affect some number of units already made which need to be rectified as per the new sketch.

Should you require further details, please feel free to contact the undersigned.

Kind Regards,

For xxx Interiors LLC

xxx

Project Manager

Leave a Comment

Your email address will not be published. Required fields are marked *

Scroll to Top