Method of Statement

toilet door frame width

Doors Method statement

FABRICATION AND INSTALLATION OF WOODEN DOORS 1.0 OBJECTIVE 1.1 Is to define the requirements for fabrication, supply and installation of wooden doors including fire rated for the buildings under the contract no GTC.101/ED/01 Engineering, Procurement, Installation and Commissioning (EPIC) of Ras Laffan Utilization Project –Buildings and utilities and support service Phase 1-Utilities. 2.0 SCOPE 2.1

Doors Method statement Read Post »

ACTIVITY HAZARD ANALYSIS Construction of Cast-in-Situ Concrete for Building structure

Concreting Method statement

CONCRETING WORKS 1.0 OBJECTIVE 1.1 Is to define the requirements for the design, supply and execution g concrete works for the constructions under the contract no GTC.101/ED/01 Engineering, Procurement, Installation and Commissioning (EPIC) of Ras Laffan Utilization Project –Buildings and utilities and support service Phase 1-Utilities. 2.0 SCOPE 2.1 For foundation, substructure and superstructure of

Concreting Method statement Read Post »

The Engineers Blog

Cavity wall Method statement

BLOCKWORK CAVITY WALL 1.0 OBJECTIVE 1.1 Is to define the method of construction and quality requirements of blockwork cavity walls for the contract no GTC.101/ED/01 Engineering, Procurement, Installation and Commissioning (EPIC) of Ras Laffan Utilization Project –Buildings and utilities and support service Phase 1-Utilities. 2.0 SCOPE 2.1 Blockwork Cavity wall for the buildings in Service

Cavity wall Method statement Read Post »

Carpet flooring Method statement

Carpet flooring Method statement

CARPET FLOORING WORKS 1.0 OBJECTIVE 1.1 To define the requirements and procedure for carpet flooring works under  the contract no GTC.101/ED/01 Engineering, Procurement, Installation and Commissioning (EPIC) of Ras Laffan Utilization Project –Buildings and utilities and support service Phase 1-Utilities. 2.0 SCOPE 2.1 Applicable to all the office buildings at Service Base Area, Service Berth

Carpet flooring Method statement Read Post »

AAC BLOCK

Block work-Method statement

CONCRETE BLOCK WORK 1.0 OBJECTIVE 1.1 Is to define the requirements for supply and laying of concrete block work for the buildings and utilities under the contract no GTC.101/ED/01 Engineering, Procurement, Installation and Commissioning (EPIC) of Ras Laffan Utilization Project –Buildings and utilities and support service Phase 1-Utilities. 2.0 SCOPE 2.1 Concrete block work for

Block work-Method statement Read Post »

ACTIVITY HAZARD ANALYSIS Backfilling of Box Culverts and Associated Structures

Method Statement for Casting of Blinding Concrete for Box Culvert and Installation of Precast Box Culvert Units

TABLE OF CONTENTS Purpose Scope of Work Definitions References Materials Plant  & Equipment Safety Prior Activities Procedure Responsibilities Attachments 1. Purpose 1.1 To ensure that the Blinding of Box Culverts and Installation of Precast Box Culvert units are executed safely and in accordance with the contract requirements and that all quality assurance/ control activities are

Method Statement for Casting of Blinding Concrete for Box Culvert and Installation of Precast Box Culvert Units Read Post »

ACTIVITY HAZARD ANALYSIS Construction of Open Concrete Formed Channel

Method Statement for Installation of Communication Sub-Ducts

CONTENTS Purpose Scope of Work Definitions References Materials Tools, Plant  & Equipment Safety Prior Activities Procedure Responsibilities Attachments Purpose 1.1       To ensure that the installation of communication sub-ducts and related activities are executed safely and in accordance with the contract requirements and that all quality assurance/ control activities are conducted in a systematic manner, works

Method Statement for Installation of Communication Sub-Ducts Read Post »

Plaster Work

Method Statement for Rendering Works for Buildings

CONTENTS Purpose Scope of Work Definitions References Materials Tools, Plant  & Equipment Safety Prior Activities Procedure Responsibilities Attachments Purpose 1.1       To ensure that the rendering works for all the buildings are executed safely and in accordance with the contract requirements and that all quality assurance/ control activities are conducted in a systematic manner, works are

Method Statement for Rendering Works for Buildings Read Post »

Scroll to Top