Mandatory Checklist for Piled Retaining Wall Foundation Design.

Mandatory Checklist for Piled Retaining Wall Foundation Design.
Mandatory Checklist for Piled Retaining Wall Foundation Design.

Designing the foundation for a piled retaining wall involves considerations for stability, bearing capacity, and soil-structure interaction. Below is a detailed checklist with explanations and examples for the design of a piled retaining wall foundation:

1. Site Investigation:

  • Explanation: Conduct a thorough site investigation to understand soil conditions.
  • Example: Perform soil tests (SPT, CPT) to determine soil properties, bearing capacity, and potential sliding or settlement.

2. Load Analysis:

  • Explanation: Analyze and calculate loads acting on the piled retaining wall.
  • Example: Consider the weight of the wall, backfill soil pressure, surcharge loads, water pressure, and seismic loads to determine the total lateral load.

3. Bearing Capacity:

  • Explanation: Ensure that the soil bearing capacity is sufficient for the applied loads.
  • Example: If the total lateral load is 200 kN/m and the soil bearing capacity is 300 kN/m², the foundation is considered suitable.

4. Sliding Stability:

  • Explanation: Check and ensure the foundation resists sliding.
  • Example: Calculate the sliding force and compare it to the resisting force provided by the foundation. Use appropriate safety factors.

5. Overturning Stability:

  • Explanation: Verify the foundation’s resistance to overturning.
  • Example: Assess the moments and forces acting on the piled wall and ensure they are counteracted by the resisting moments and forces provided by the foundation.

6. Foundation Geometry:

  • Explanation: Determine the appropriate dimensions and shape of the foundation.
  • Example: Design a piled foundation with the required number and spacing of piles to distribute the loads evenly along the length of the retaining wall.

7. Pile Selection:

  • Explanation: Select appropriate pile types based on soil conditions and design requirements.
  • Example: Choose driven piles or bored piles depending on the soil profile and load-carrying capacity needed.

8. Pile Spacing and Arrangement:

  • Explanation: Determine the optimal spacing and arrangement of piles for stability.
  • Example: Space the piles evenly along the wall length and provide additional reinforcement where required.

9. Pile Length:

  • Explanation: Calculate the required length of the piles to reach load-bearing strata.
  • Example: If the competent soil layer is 10 meters below the ground surface, design piles with lengths exceeding 10 meters to ensure adequate embedment.

10. Pile Cap Design:

  • Explanation: Design the pile cap to distribute loads to individual piles.
  • Example: Include a reinforced concrete pile cap with appropriate dimensions and reinforcement to transfer loads from the retaining wall to the piles.

11. Reinforcement:

  • Explanation: Specify reinforcement in the foundation and pile cap, if required.
  • Example: Include reinforcing bars in the pile cap to enhance its tensile strength and improve overall stability.

12. Pile Installation:

  • Explanation: Specify procedures for pile installation.
  • Example: Require proper driving or boring techniques and procedures to achieve the desired pile lengths and capacities.

13. Testing and Monitoring:

  • Explanation: Include provisions for pile load testing and monitoring during construction.
  • Example: Conduct a static load test on selected piles to verify their capacity and assess the performance of the foundation.

14. Drainage:

  • Explanation: Implement drainage measures to reduce hydrostatic pressure.
  • Example: Install drainage pipes around the pile caps to prevent water accumulation and reduce the risk of soil liquefaction.

15. Backfill Compaction:

  • Explanation: Specify compaction requirements for the backfill soil.
  • Example: Compaction should be done in lifts with specified moisture content to achieve adequate density.

16. Construction Sequence:

  • Explanation: Develop a construction sequence that ensures stability during and after construction.
  • Example: Install piles, construct the pile cap, and then build the retaining wall while monitoring for settlement or other issues.

17. Quality Control:

  • Explanation: Implement quality control measures during construction.
  • Example: Monitor pile installation for proper alignment and penetration, check reinforcement placement, and verify the dimensions of the pile cap.

18. Code Compliance:

  • Explanation: Ensure compliance with local building codes and standards.
  • Example: Adhere to relevant codes such as AASHTO LRFD Bridge Design Specifications or local geotechnical standards.

19. Professional Engineer Involvement:

  • Explanation: Engage a qualified geotechnical and structural engineer to oversee the design.
  • Example: Have licensed engineers review and approve the piled retaining wall foundation design to ensure it meets safety and code requirements.

20. Record Keeping:

  • Explanation: Maintain detailed records of the piled retaining wall foundation design process.
  • Example: Document all design calculations, soil test results, construction activities, and as-built drawings for future reference and audits.

By following this checklist, engineers can ensure a well-designed piled retaining wall foundation that effectively resists lateral loads, provides stability, and minimizes potential failure modes.

By Md Abu Zaed Khan

Hello, this is Engr. Zaed Khan Planning Engineer, Associate member of Society of Engineers UAE. Expert in construction project planning, FIDIC red book, computation of extension of time claim, Contract agreement and contractual letters.

Leave a comment

Your email address will not be published. Required fields are marked *

Exit mobile version