DE moisture mirror

LPO for the Mirror for Typical Floor

Date:               xxx

Ref:                  xxx

Kind Attn         :Mr. xxx

Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai

Subject:Regarding the LPO for the Mirror for Typical Floor

Dear Sir,

With reference to the above subject, we informing you that we already sent the LPO with reference no.830138 dated on xxx to xxx Glass & Mirror Stores for the Mirror and meantime the Mirror for Typical floor needs 40 days to fix.

Futhermore, your statement for imperative completion date will be on June 18, 2018 and kindly review our latest program R17 submitted May 3, 2018. Our plan date for Dubai Municipality application will be 1st July 2018 as well as this item is not in critical line for any inspection and we are more concern for the testing and commissioning.

This is for your kind information and record.

Regards,

For xxx Contracting L.L.C.

xxx

Project Manager