Ref: xxx
Date: xxx
To:
P.O Box: xxx
Tel: xxx, Fax: xxx
Project : 2B+G+7 Residential Building, ICP1 CBD C01, International City
Client : M/s xxx Properties Ltd
Consultant : M/s xxx Engineering Consultant.
Subject: Gas Tank Installation
Dear Sir
With reference to the above mentioned subject, we would like to inform you that you need to speed up and complete the work as soonest because related work for
Civil Defense were also delayed.
Also, we are requesting you to send us your Check and Priority List with regards to your work at site for us to know what are remaining works and related works need to prioritized particularly the Installation of Gas Tank to us to do the parallel with other activity.
As we all know we only have small remaining time for the handing over of the building.
So, please do the necessary works.
In this regards your cooperation is highly appreciated.
Thanking you
For xxx Contracting LLC
xxx