Site Meeting

Inspection of ledge wall and comments

Date:               xxx

Ref:                  xxx

Kind Attn         :Mr. xxx

Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai

Sub    : Inspection of ledge wall and comments as well as site meeting on Monday dtd-xxx with Denloex/Client/Consultant.

Dear Sir,

With reference to above, we would like to update for the ledge wall issue for approval and note the following.

1. The sample fixed on unit no 5 was recommented and instructed to fix two no’s more sample. 

2. One new sample to be fixed without projection at all three side and it must be fit to size of Ledge wall with curve edge similar to PVC tile corner.

3. Another sample required only projection at front side in lengthwise and no projection in widthwise.

So, we instructed the sub contractor to fix two more sample and we will raise the inspection after execution. 

This is for your kind information and record. 

Regards,

For xxx Contracting L.L.C.

xxx

Project Manager