M/s xxx Building Contracting Co. LLC

Office No. xxx

Dusseldorf Business Point

P.O Box xxx, Al Barsha 1, Dubai, UAE

Tel:  xxx

Fax: xxx

Attention          :           Eng. xxx

                                     Procurement Manager

Project             :           The Living Legends, Dubailand

Subject:            External Doors

Dear Sir,

We acknowledged receipt of your letter reference xxx dated 30th December xxx in response to our letter reference xxx dated 28th December xxx regarding the delayed payment, and we refute your statement referring to Clause 8, Article 6 that the payment is not due till date.

Please be informed that the Clause 8, Article 6 which you have referred to, refers to the rights of the Second Party to suspend the works in case the payment is not received within 60 days from the date of the payment certificate and not the due date of the payment.

We would like to refer you to the Clause 9 – Payment Terms where it was clearly stated that the payment due date will be 30 days from Second Party’s payment certificate, therefore, our payment is already been due in accordance with the Subcontract Agreement.

In view of the foregoing, we request your assistance in the release of our due payment at the earliest

Sincerely Yours,

For Xxx (Name of the Subcontractor) Interiors LLC

xxx                             

Head of Sales & Marketing