Site icon The Engineers Blog

Extension of time claim to complete the project.

Extension of time claim to complete the project.

Extension of time claim to complete the project.

An Extension of Time (EOT) claim in a construction project is a formal request by the contractor to extend the project’s completion date beyond the original contractual deadline. This claim is made when delays occur that are beyond the contractor’s control, such as changes in project scope, adverse weather conditions, or unforeseen site conditions. The EOT claim allows the contractor additional time to complete the project without being subject to penalties for late completion, such as liquidated damages.

An EOT claim ensures that the contractor is not held liable for delays they cannot control and can help maintain a positive working relationship between the contractor and the client (or employer). In most contracts, particularly those that follow standard forms such as FIDIC, JCT, or NEC, there are provisions for extending time when justified.

Key Concepts in an Extension of Time Claim:

  1. Delay Events:
  1. Contractual Provisions:
  1. Liquidated Damages:
  1. Submission Timeline:

Types of Delays:

  1. Excusable Delays:
  1. Non-Excusable Delays:
  1. Compensable Delays:
  1. Non-Compensable Delays:
  1. Concurrent Delays:

Steps for Making an Extension of Time Claim:

  1. Identify the Delay Event:
  1. Notify the Client:
  1. Prepare Supporting Documentation:
  1. Assess the Impact on the Critical Path:
  1. Submit the EOT Claim:
  1. Negotiation and Resolution:
  1. Approval and Issuance of Revised Completion Date:

Example of an Extension of Time Claim:

Scenario:
A contractor is building a commercial office building with a contract completion date of December 31. During the construction, the contractor encounters unexpected groundwater during foundation excavation, which was not identified in the initial geotechnical report.

Steps for EOT Claim:

  1. The contractor notifies the client on January 10, explaining that the groundwater issue will cause delays to the foundation work.
  2. The contractor submits evidence, including daily reports, engineering assessments, and updated schedules showing the impact on the project’s critical path.
  3. The claim requests an additional 30 days to complete the project, moving the completion date to January 31.
  4. After reviewing the documentation, the client agrees that the unforeseen groundwater issue was outside the contractor’s control and grants the 30-day extension.

Factors Affecting the Success of an EOT Claim:

  1. Timeliness of Submission:
  1. Clear Documentation:
  1. Contractual Clauses:
  1. Client Cooperation:
  1. Expert Input:

Consequences of Not Filing an EOT Claim:

Conclusion:

An Extension of Time (EOT) claim is a crucial process for contractors to manage delays in a construction project that are beyond their control. By properly identifying, documenting, and submitting an EOT claim, contractors can avoid financial penalties and ensure they are given the time necessary to complete the project. Success in EOT claims depends on clear communication, strict adherence to contractual terms, and strong documentation to support the claim. Understanding the types of delays and their impacts on the project schedule is essential to protect both the contractor’s and the client’s interests.

Exit mobile version