Different types of change orders, why and when its issued.

Different types of change orders, why and when its issued.

A Change Order is a document used in construction projects to officially modify the scope, schedule, or budget of a contract. It is issued when there is a need to make alterations to the original agreement between the client and the contractor. Change Orders provide a formal mechanism for documenting and approving changes to the project, ensuring clarity and accountability for all parties involved.

Types of Change Orders:

  1. Scope Change Order:
  • A scope change order is issued when there is a need to alter the project’s scope of work. This could involve adding, removing, or modifying specific tasks or deliverables.
  • Example: In a building construction project, the client decides to add an additional floor to the original design. A scope change order would be issued to document this change and outline the new scope of work, including any adjustments to the schedule and budget.
  1. Schedule Change Order:
  • A schedule change order is issued when there is a need to adjust the project timeline or sequencing of activities.
  • Example: Due to unforeseen weather delays, the completion date for a landscaping project needs to be extended by two weeks. A schedule change order would be issued to formally document the new timeline and any associated adjustments to deadlines or milestones.
  1. Cost Change Order:
  • A cost change order is issued when there is a need to modify the project budget. This could involve increasing or decreasing the total contract amount.
  • Example: During the course of a renovation project, the client decides to upgrade the flooring material to a higher-quality option. A cost change order would be issued to reflect the additional expense associated with the upgraded materials and any adjustments to the overall budget.
  1. Design Change Order:
  • A design change order is issued when there is a need to modify the project’s design or specifications.
  • Example: In a commercial construction project, the architect revises the interior layout of the office space to accommodate additional workstations. A design change order would be issued to document the revised design and any associated adjustments to the scope, schedule, or budget.

Why and When Change Orders are Issued:
Change orders are typically issued in response to unforeseen circumstances, client requests, or changes in project requirements. They are necessary to ensure that any modifications to the original contract are properly documented and approved by all parties involved. Change orders are issued when:

  • There are changes to the project scope, schedule, budget, or design.
  • Unforeseen conditions arise during construction that require modifications to the original plan.
  • The client requests changes to the project requirements or specifications.
  • Errors or omissions are discovered in the original contract documents.
  • Regulatory requirements or building codes change during the course of the project.

Issuing change orders helps to maintain transparency, accountability, and clear communication between the client, contractor, and other stakeholders. It also helps to mitigate disputes and minimize the risk of project delays or cost overruns by addressing changes in a structured and systematic manner.