Project : xxx Towers Project, Dubai
Subject: Delivery Schedule
Dear Mr. Loh,
We refer to our letter Ref: xxx dated xxx and subsequent emails related to the delivery schedule, including the revised schedule received from your end on the 30th of September xx.
Attached you will find a tentative programme based on the following assumptions.
- We will receive from your end the approvals on all drawings by Thursday, 3rd October xxx.
- We will receive from your end the full set of free issue items to enable us to complete the pods on or before Saturday, 5th October xxx.
- The schedule is prepared based on the following lead times and cycle.
- From the date of receiving your approval on the drawings, it takes:
- 2-4 days to complete the production drawings (2 pods per day; 4 days cycle)
- 2-3 days to build the moulds and programme the machines for the wall and ceilings fabrication (2 moulds per day)
- 15 days production cycle to complete the pods.
Please rest assured that Xxx will do whatever is technically possible to assist you in getting the pods as fast as possible.
Yours faithfully,
On behalf of xxx LLC