Deference between prime cost and provisional sum items.
Introduction
In construction contracts, both Prime Cost (PC) items and Provisional Sum items serve to address uncertainties regarding certain materials, work, or services. However, while they may appear similar, they serve distinct purposes and have different methods of estimation and management. Below is a comprehensive breakdown of the differences between Prime Cost and Provisional Sum items, focusing on their definitions, purposes, calculation methods, and practical use in construction projects.
1. Definition
- Prime Cost (PC) Items: These refer to materials or goods specified in the contract whose exact brand, model, or type is not determined at the time of signing. The cost relates specifically to the supply of these materials, excluding labor or installation costs. Prime Cost items typically apply to material choices (e.g., bathroom fittings, kitchen appliances) that are to be selected later by the client.
- Provisional Sum Items: These represent estimated budget allocations for work or services that are not fully defined at the time of contract signing. The scope, quantity, or specific requirements of the work are unknown, and the sum may include labor, materials, and related overheads. Provisional sums cover a broader range of undefined work, including unforeseen site conditions or future client decisions on services.
2. Purpose
- Prime Cost Items: The purpose of Prime Cost items is to provide flexibility in choosing specific materials or goods during the project. This allows the project to proceed without being delayed while waiting for the client to finalize certain decisions on items like tiles, taps, or appliances.
- Provisional Sum Items: Provisional sums are used to cover work or services where there is uncertainty about the scope or need for those works at the time of contracting. This could be for tasks such as landscaping, groundworks, or mechanical installations, where the exact requirements will only become clear as the project progresses.
3. Scope
- Prime Cost Items: The scope of a Prime Cost item is limited strictly to the material or product itself. It excludes labor or installation costs, focusing only on the supply cost of a specified material that will be chosen later.
- Provisional Sum Items: Provisional sums have a broader scope as they can cover entire works or services, including both labor and materials. They apply to incomplete or undefined sections of a project and could be used for entire components like earthworks, electrical services, or landscaping.
4. When Applied
- Prime Cost Items: PC items are applied when the client has not yet selected the exact materials or finishes but knows that these items will be required. They are mostly used for elements like fixtures and finishes (e.g., taps, tiles, sinks) in residential or commercial buildings.
- Provisional Sum Items: Provisional sums are applied when the contractor and client are unsure of the exact requirements for certain work or services. This could be due to incomplete design, unforeseen site conditions, or specialized work that needs to be determined at a later stage (e.g., foundation work depending on ground conditions).
5. Examples
- Prime Cost Examples:
- Bathroom Fixtures: The client may not have decided on the exact type of taps, sinks, or showers at the time of signing. A Prime Cost allowance of $5,000 might be included for these fixtures, with adjustments made once the client chooses specific brands or models.
- Tiles or Flooring: The exact type of tile may not have been finalized, so an allowance of $30 per square meter could be set as a Prime Cost, adjusted after the tiles are selected.
- Provisional Sum Examples:
- Landscaping: The exact design and requirements for landscaping may be unclear during the early construction phases, so a Provisional Sum of $50,000 could be allocated to cover it until the scope is defined.
- Groundworks: If there is uncertainty about the condition of the site, a Provisional Sum could be included to cover potential additional groundworks, such as soil stabilization or drainage installation.
6. Calculation
- Prime Cost Items: The Prime Cost is calculated based on an estimate of the market rate for mid-range or commonly used materials or goods in that category. The contractor estimates the cost of materials like tiles, fixtures, or appliances based on average prices for items that meet the project’s standards, even if the exact selection has not yet been made. Example: If the client wants bathroom tiles but hasn’t chosen a specific type, the contractor might allocate $30 per square meter based on standard mid-range tile prices. Once the client selects tiles costing $40 per square meter, the final cost will be adjusted.
- Provisional Sum Items: Provisional sums are calculated based on an estimated cost for work that is not fully scoped. These sums cover labor, materials, and other related expenses. The estimation process typically draws on past project data, industry norms, or consultation with specialized subcontractors to approximate what the work might cost. Example: For groundworks, the contractor may not know the exact amount of excavation or reinforcement required, so a Provisional Sum of $20,000 is set. After site conditions are fully assessed, the actual cost of the work might come in at $25,000, requiring an adjustment.
7. Adjustments and Finalization
- Prime Cost Items: Once the client makes a final decision on the specific product or material (e.g., choosing a particular brand of tap or tile), the cost is adjusted. If the selected items cost more or less than the estimated Prime Cost, the final project budget is updated accordingly. Adjustment Example: If the estimated cost for bathroom fixtures was $3,000 (Prime Cost), but the client selects fixtures worth $4,500, the client pays an additional $1,500.
- Provisional Sum Items: Provisional sums are adjusted once the exact scope of the work is determined or after additional assessments are made (e.g., site surveys, detailed designs). If the actual cost of completing the work exceeds or falls below the provisional sum, the contract is adjusted to reflect the true cost. Adjustment Example: If a Provisional Sum of $30,000 was included for landscaping but the final cost, based on the agreed design, comes out at $35,000, the client will need to cover the extra $5,000.
8. Client Involvement
- Prime Cost Items: The client is typically highly involved in the final decision-making for Prime Cost items. They are responsible for selecting the specific products or finishes that fit within or exceed the allocated budget.
- Provisional Sum Items: The client’s involvement in Provisional Sum items is often less direct. These sums are usually used for items or services that are determined through site conditions, technical requirements, or design developments. However, the client may be consulted when finalizing certain provisional sum items, such as choosing between different solutions for unforeseen issues.
9. Financial Flexibility
- Prime Cost Items: Prime Cost items offer flexibility in material selection, allowing clients to upgrade or downgrade items as needed based on their preferences or budget. This is particularly useful for finishes and fixtures that may evolve with design preferences over time.
- Provisional Sum Items: Provisional sums offer flexibility for undefined work that cannot be scoped at the time of contract signing. They are helpful in accommodating unforeseen site conditions, additional work requirements, or services that emerge as the project progresses.
Key Differences Summary
Aspect | Prime Cost Items | Provisional Sum Items |
---|---|---|
Definition | Material or goods with undefined specifics. | Estimated costs for undefined work or services. |
Purpose | Allows flexibility in choosing specific materials. | Covers work/services that are not yet fully defined. |
Scope | Limited to material costs (excludes labor). | Covers both labor and materials for undefined works. |
Examples | Bathroom fittings, tiles, kitchen appliances. | Landscaping, groundworks, mechanical services. |
Calculation | Based on estimated material prices. | Estimated based on previous projects or professional judgment. |
Adjustment | Adjusted after the client makes material decisions. | Adjusted when the exact scope of work is defined. |
Client Involvement | Client actively selects materials later in the process. | Client is less involved unless major design decisions arise. |
Financial Flexibility | Offers flexibility in material upgrades/downgrades. | Offers flexibility for undefined work and contingencies. |
Conclusion
Both Prime Cost and Provisional Sum items are essential tools for managing uncertainty in construction projects. Prime Cost items are used when the specific materials or finishes are yet to be selected but are known to be required, giving clients the flexibility to make choices later. Provisional Sum items, on the other hand, cater to undefined or uncertain work that may depend on site conditions, evolving designs, or unforeseen circumstances, providing a buffer to ensure the project progresses smoothly without stopping for design or scope decisions.
Understanding the difference between these two concepts helps both contractors and clients navigate the financial and contractual complexities of construction projects more effectively, ensuring that potential adjustments to scope and cost are anticipated and managed with transparency.