M/s xxx Building Contracting LLC
PO Box xxx, Dubai, U.A.E
T: xxx | F: xxx
Email: xxx
Attention : MR. xxx
Project Manager
Project : xxx Sky Tower – Umm Ramool
Subject : Damages to Joinery Works
Dear Sir,
We would like to draw your attention to the continuous damages being done on the installed joinery works due to the incomplete works by others which will affect the project completion due to the required rectification (refer to the attached details).
In view of this, Xxx (Name of the Subcontractor) Interiors reserve its rights to claim for additional cost and extension of time due to the necessary rectification required, all the relevant details will be submitted in due course.
This is for your information, reference and record.
Sincerely Yours,
For Xxx (Name of the Subcontractor) Interiors LLC
xxx
Commercial Manager