Date: xxx.
Ref.: xxx
Total Pages: 1
To,
xxx
P.O Box: xxx, Dubai, UAE
Phone: +xxx
Attention: xxx – Principal
Project: xxx.
Reference: xxx
Subject: Nominated Subcontractor M/s. xxx Aluminum & Glass Contractors payment terms and retention issue
Dear Sir,
This is further to our subsequent discussion regarding client nominated subcontractor M/S Souhail Jaber Aluminum & Glass Contractors for sliding windows works, we want to put on record that as per your email confirmation (copy attached) we are entering a subcontract agreement with M/s. Souhail Jaber Aluminum & Glass Contractors for the aforesaid works with 60% advance of total contract value without securing bank guarantee/security cheque and 5% retention provision for DLP.
Therefore, the client will take sole responsibility/risk of advance payments, subcontractor performance of the site and during DLP.
This is for your information and record.
Yours Sincerely,
xxx