RE- Compliance to Consultant issued snagging comments for first floor

Our Ref: xxx Date: xxx To                           xxx Contracting Company LLC P. O. Box xxx, Dubai, U.A.E. Attention            : Mr. xxx, Senior Project Manager Project                 : xxx Tower, Dubai – U.A.E. Subject                 : RE- Compliance to Consultant issued snagging comments for first floor References         : a) UP-1763/LET-1373-21/LS-at dated 29 September xxx   b) xxxdated 11 March […]

RE- Compliance to Consultant issued snagging comments for first floor Read Post »

Response to Delay in Delivery of PODs

Our Ref: xxx Date: xxx To                           xxx Contracting Company LLC P. O. Box xxx, Dubai, U.A.E. Attention            : Mr. xxx, Senior Project Manager Project                 : xxx Tower, Dubai – U.A.E. Subject                 : RE- Compliance to NCR & site instructions References         : a) xxx dated 11 March xxx   b) xxx dated 15 December xxx  Dear

Read Post »

Project Manager

Response to Design Guardian Site Observation Report No. xxx

Our Ref: xxx Date: xxx To                           xxx Contracting Company LLC P. O. Box xxx, Dubai, U.A.E. Attention            : Mr. xxx, Senior Project Manager Project                 : xxx Tower, Dubai – U.A.E. Subject                 : Response to Design Guardian Site Observation Report No. xxx Reference          : a) xxx dated 28 September xxx                                   b) xxx dated 15

Response to Design Guardian Site Observation Report No. xxx Read Post »

Engineer's Instruction

RE- Compliance to Consultant Issued Site Instruction No. xx

Our Ref: xxx Date: xxx To                           xxx Contracting Company LLC P. O. Box xxx, Dubai, U.A.E. Attention            : Mr. xxx, Senior Project Manager Project                 : xxx Tower, Dubai – U.A.E. Subject                 : RE- Compliance to Consultant Issued Site Instruction No. xx Reference          : xxx dated 18 March xxx Dear Sir, We are in receipt of

RE- Compliance to Consultant Issued Site Instruction No. xx Read Post »

Tile

Status of tiles TL-202

Our Ref: xxx Date: xxx To                           xxx Contracting Company LLC P. O. Box xxx, Dubai, U.A.E. Attention            : Mr. xxx, Senior Project Manager Project                 : xxx Tower, Dubai – U.A.E. Subject                 : Status of tiles TL-202 Reference           : a) xxx dated 15 December xxx                                 b) xxx dated 14 January xxx                                   c) xxx

Status of tiles TL-202 Read Post »

Response to Delay in Delivery of PODs

Response to Design Guardian Site Observation Report No. xxx

Our Ref: xxx Date: xxx To                           xxx Contracting Company LLC P. O. Box xxx, Dubai, U.A.E. Attention            : Mr. xxx, Senior Project Manager Project                 : xxx Tower, Dubai – U.A.E. Subject                 : Response to Design Guardian Site Observation Report No. xxx Reference          : a) UP-1763/LET-1333-21/LS-ng dated 15 December xxx                               b) UP-1763/LET-1344-22/LS-at dated 14 January

Response to Design Guardian Site Observation Report No. xxx Read Post »

Undertaking Letter for the MS Ceiling Frame

RE-False ceiling suspension and board closing programme from 1st to 20th floor.

Our Ref: xxx Date: xxx To                           xxx Contracting Company LLC P. O. Box xxx, Dubai, U.A.E. Attention            : Mr. xxx, Senior Project Manager Project                 : xxx Tower, Dubai – U.A.E. Subject                 : RE-False ceiling suspension and board closing programme from 1st to 20th floor. Dear Sir, We are in receipt of your letter ref: xxx

RE-False ceiling suspension and board closing programme from 1st to 20th floor. Read Post »

Tiles and other Prime Cost items

Status of tiles TL-202 & other free issue materials.

Our Ref: xxx Date: xxx To                           xxx Contracting Company LLC P. O. Box xxx, Dubai, U.A.E. Attention            : Mr. xxx, Senior Project Manager Project                 : xxx Tower, Dubai – U.A.E. Subject                 : Status of tiles TL-202 & other free issue materials. Reference           : a) xxx dated 15 December xxx                                 b) xxx dated 14 January

Status of tiles TL-202 & other free issue materials. Read Post »

shake-up-sales-meeting

RE- Compliance to NCR & site instructions

Our Ref: xxx Date: xxx To                           xxx Contracting Company LLC P. O. Box xxx, Dubai, U.A.E. Attention            : Mr. xxx, Senior Project Manager Project                 : xxx Tower, Dubai – U.A.E. Subject                 : RE- Compliance to NCR & site instructions References         : a) xxx dated 11 March xxx   b) xxx dated 15 December xxx   

RE- Compliance to NCR & site instructions Read Post »

Engineer's Instruction

RE- Compliance to Consultant Issued Site Instruction No. xxx

Our Ref: xxx Date: xxx To                           xxx Contracting Company LLC P. O. Box xxx, Dubai, U.A.E. Attention            : Mr. xxx, Senior Project Manager Project                 : xxx Tower, Dubai – U.A.E. Subject                 : RE- Compliance to Consultant Issued Site Instruction No. xxx Dear Sir, We are in receipt of your letter ref: xxx dated 15 March