Project: (G+23) Building 4 Nos. in Dubai
Subject : Completion of Defects Liability Period
Dear Mr. xxx,
We refer to our Work Order xxx dated 7th January xxx regarding the Lake Side project and to our subsequent letter dated 9th August xxx addressed to M/s ZAS/PSE regarding the request for the Completion Certificate and the release of the retention amount for the above referred project.
Please be informed that the defects Liability Period of 90 calendar days as per the contract is deemed to be completed by the 15th November xxx, therefore, we expect the release of our final payment upon completion of the DLP.
This is for your information and necessary action.
Thanks & regards,