COMPLETION & HANDING OVER OF SNAG WORKS
M/s xxx Property Investment
P.O Box xxx,Dubai,UAE
Tel: xxx
Fax: xxx
Attention : Mr. xxx
Project Coordinator
Project : Multi-Use Complex ( xxx Hotel ) on Plot No. xxx
at Al Barsha First, Dubai
Subject : COMPLETION & HANDING OVER OF SNAG WORKS
Dear Sir,
With reference to the above project, and the Letter of Award (LOA) Ref: xxx dated 29th August xxx, herein, we informed that our contractual obligation towards the completion of the below listed snag works is now satisfactorily completed and handed over on 27th February xxx in accordance to the Contract Documents.
DESCRIPTION | SNAGS | ACTION |
365 Restaurants | Buffet skirting has bubbles / cracks that needs to be changed | Completed |
Floor parquet gets damaged continuously | Completed | |
Business Center | Outside wall wooden panel came out | Completed |
Carvin Cajun Restaurants | Buffet wooden counter has cracks | Completed |
In view of the above, we hereby request the release of the DLC (Defects Liability Certificate) and our retention money.
Kind Regards,
For: xxx Interiors LLC