Completion Certificate and Retention Payment

Completion Certificate and Retention Payment

M/s xxx Properties LLC

P. O. Box xxx, Dubai, UAE

Tel: xxx

Fax: xxx

Attention:         Mr. xxxAssistant Manager – Commercial          

Project:            (G+23) Building 4 Nos. in Dubai

Subject           :  Completion Certificate and Retention Payment

Dear Mr. Abdullah,

We refer to our Work Order xxx dated 7th January xxx regarding the Lake Side project and to our subsequent letter dated 9th August xxx (copy attached) addressed to M/s xxx regarding the request for the Completion Certificate and the release of the retention amount for the above referred project.

Please be informed that to date we have not received the requested completion certificate and the payment of the retention amount. In this regard, we really appreciate your assistance in expediting the issuance of the Completion Certificate and the release of the AED xxx which corresponds to the first 5% retention amount.

This is for your information and necessary action.

Thanks & regards,

For Xxx (Name of the Subcontractor) Interiors LLC:

xxx

Commercial Manager