Site icon The Engineers Blog

Collapsed As-Built (or “But For” Analysis) in Construction

Collapsed As-Built (or "But For" Analysis) in Construction

Collapsed As-Built (or "But For" Analysis) in Construction

Introduction

The Collapsed As-Built Analysis, often called the “But For” Analysis, is a delay analysis technique used to evaluate the impact of specific delay events on the overall project completion date. The key concept of this technique is to assess the question: “But for the delay events, when would the project have been completed?”

In essence, it involves removing the delays from the as-built schedule to understand how the project would have progressed if those delay events had not occurred. This technique is often used in retrospective claims to justify an Extension of Time (EOT) or to determine responsibility for delays.

Key Components of Collapsed As-Built Analysis

  1. As-Built Schedule:
  1. Identification of Delay Events:
  1. Removing Delay Events:
  1. Impact Assessment:

Steps in Collapsed As-Built Analysis

1. Prepare the As-Built Schedule:

The starting point for the analysis is the as-built schedule, which shows the actual dates of activities and the overall project completion date. This schedule reflects all delays and disruptions that occurred during the project.

2. Identify Delay Events:

The next step is to identify the specific delay events that occurred. These delays may include:

3. Remove Delay Events:

Once the delay events are identified, they are removed from the as-built schedule to create the “collapsed” schedule. The purpose of this is to determine when the project would have finished had those delay events not occurred. This step involves:

4. Compare Collapsed As-Built vs. As-Built:

The collapsed as-built schedule is compared to the original as-built schedule. The difference between the two indicates the impact of the delay events on the project completion date.

5. Determine Responsibility and Impact:

Example of Collapsed As-Built Analysis

Scenario:

A contractor is building a residential apartment complex. The project was originally planned to be completed by December 31, but the actual completion date (as-built) was February 28. During the project, several delays occurred, including:

Step 1: As-Built Schedule

Step 2: Identify Delay Events

Step 3: Remove Delay Events

Step 4: Create Collapsed As-Built Schedule

Step 5: Compare Collapsed As-Built vs. As-Built

Step 6: Determine Responsibility

Result:

Advantages of Collapsed As-Built Analysis

  1. Clear Causation of Delays: This technique is useful in identifying which specific delays caused the project’s extension, helping to clarify responsibility.
  2. Suitable for Complex Projects: It is especially effective in projects with multiple delays and disruption events, as it helps break down which events contributed to the delay.
  3. Ideal for Retrospective Claims: It provides a clear picture of the past events and how they impacted the project schedule, making it ideal for dispute resolution or litigation.

Disadvantages of Collapsed As-Built Analysis

  1. Subjective Interpretation: There is some subjectivity in determining which delays should be removed and how to handle concurrent delays.
  2. Data-Intensive: This method requires detailed project records and documentation to accurately assess the impact of each delay.
  3. Potential for Over-Simplification: By removing delays, the analysis may oversimplify the complex interactions between activities and events, missing out on concurrent delays or mitigation efforts that were undertaken during the project.

Application in Dispute Resolution

The Collapsed As-Built Analysis is commonly used in arbitration, mediation, or litigation when the contractor and client dispute responsibility for delays. It helps demonstrate the impact of delays on the overall project completion and is particularly effective in cases where the project has multiple delays and disruptions that need to be carefully dissected.

Conclusion

The Collapsed As-Built Analysis (But For Analysis) is a powerful delay analysis technique used to assess the impact of specific delay events on a construction project. By removing delays from the as-built schedule, it provides insight into when the project would have been completed “but for” those delays. This method helps identify the cause and responsibility of delays and is widely used in Extension of Time (EOT) claims and dispute resolution. Proper documentation, a well-maintained as-built schedule, and accurate delay identification are crucial to the success of this analysis technique.

Exit mobile version