Project                     : 2B+G+7 Residential Building, ICP1 CBD C01, International City

Client                       : M/s xxx Properties Ltd

Consultant             : M/s xxx Engineering Consultant.

Subject: Check and Priority Lists with Confirmation Date

Dear Sir

With reference to the above mentioned subject and as yesterday meeting discussion. We would like to inform you that you need to send us today the ff:

  1.  Check and Priority List  work particular at  Roof Area
  2. Duct reduce size at Lift Lobby Area ( Lower Roof)
  3. Ground Floor Lift lobby Clearance

With this  we come to know  what are remaining works and related works need to be prioritized, to us to do the parallel with other activity.

As we all know we only have small remaining time for the handing over of the building.

So, please do the necessary works.

In this regards your cooperation is highly appreciated.

Thanking you