casting of pool area beam which was hold due to opening issue and MEP work

casting of pool area beam which was hold due to opening issue and MEP work

Date:               xxx

Ref:                  xxx

Kind Attn         :Mr. xxx

Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai

Subject      : Regarding casting of pool area beam which was hold due to opening issue and MEP work.

Dear Sir,

We would like to inform you that pool area beams we are casting after your verbal confirmation that no opening allowed through beam and another proposal was discussed in your office yesterday. 

Mean time kndly note the following. 

  1.  As per decision verbally for fresh air and lighting below pool slab, confirmed by client before to submit your office for fresh air and lighting and your review to be used during any maintaince at confined space below pool. 
  2. We did rework to Provide exhaust fan through beam and air will discharge toward ramp side elevation with 200×200 sqmm self opening lowered. 
  3. The opening in beams for exhaust and lights position as well as operating switch drawing submitted to your office and approval awaited, variations detail will be submitted after approval along with slab cutting to provide access through slab. 
  4. As per verbal confirmation by client, needs to be confirmed by your office from client.
  5.  The slab cutting and other issue will be deal separately after approval the drawing that will be submitted as soon as possible to your good office

So, we are proceeding to casting the beam with variation work proposed for MEP service as required for pool sub con con and needs to approve the drawing as well as variation work that will be raised in future during maintenance in future.

Regards,

For xxx Contracting L.L.C.

xxx

Project Manager