Follow up of approval/feedback of our submitted variation order request 9, 10 and 11

Follow up of approval/feedback of our submitted variation order request 9, 10 and 11

Date: xxx.

Ref.: xxx

Total Pages: 1

To,

xxx

P.O Box: xxx, Dubai, UAE

Phone: +xxx

Attention:        xxx – Principal

Project:            xxx.

Reference:       xxx

Subject:          Follow up of approval/feedback of our submitted variation order request 9, 10 and 11

Dear Sir,

With reference to the above-mentioned subject and we would like to follow up of approval/feedback for the following variation order request.

To claim variation works in our interim invoice we must secure official approval from your good office including client approval as mentioned variations works has been completed at site. However, you have confirmed verbally that variation order request of 10 and 11 were approved during site progress meeting.

However, we have verbal confirmation for variation order request of 10 and 11, but we want to secure official approval from your good office including client approval.

SL No.Variation Order request No.Variation Order Request DetailsDate of Submission
1V.O No. – 09Prolongation Cost22-Mar-20
2V.O No. – 10Compound Wall07-Apr-20
3V.O No. – 11Core cutting for MEP Services07-Apr-20

This is for your kind action and approval.