Date: xxx
Ref no: CC/DEWA/002/17
To,
Mr. Marwan Karani
Head of the Inspection Department
Dewa,Dubai
Project : 2B + G + 14+ Lower Roof Hotels Building on Plot No. 373-1297 at Barsha, Dubai
Client : Al Sheikh Faisal Bin Khalid Sultan Al Qassemi.
Subject : Application no –E964644 for substation inspection and our under taking letter for Tower carne as well as logistic support to shift the transformer.
Dear Sir,
We would like to request you to receive the substation inspection was completed our application no–E964644 butnot cleared finally due to existing tower crane near substation door and kindly note the following.
- There is sufficient space for substation equipment’s and maintainer at presence of temporary tower crane.
- We will assist as much as required by Dewa during their mobilization or any work from Dewa.
- We are here by confirming that the temporary tower crane will be removed immediately after the construction work
- Meantime we are attaching our consultant confirmation that for external paint approval by consultants.
So, kindly consider our request and review the drawing attached with our under taking to clear the inspection and receive the substation.
Thanks in advance and your cooperation and support to the project completion.
For xxx Contracting L.L.C
xxx
General Manager