Our Ref: xxx
Date:
To
xxx Contracting LLC
P. O. Box xxx
Dubai, U.A.E.
Attention : Mr. xxx, Group Procurement Manager
Related posts:
Snagging Report for Flat 406 and 408 in Building-1
Regards to the Hotel Operator’s Comments and Our Concern
Project : xxx Phase 2
Subject : EMPLOYERS REPRESENTATIVES INSTRUCTION (ERI-009) – CANCELLATION OF
FLOOR ACOUSTIC UNDERLAY
Dear Sir,
Please be informed that the Floor Acoustic Underlay is not part of our scope. Therefore, the Employer’s Instruction (009) and request for cost saving does not apply to us.
Yours faithfully,
On behalf of xxx LLC
xxx
project Manager