Date: xxx
Ref: xxx
Kind Attn :Mr. xxx
Project: 2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai
Subject : Regarding aluminum and plaster work and issue with façade lighting
Dear Sir,
With reference to the above, as we have an advance drawing of façade lighting copy and we also
intimated in our letter references CC/AP/438/17 dtd. 03.06.17 and CC/AP/406/17 dtd. 07.05.17, there
we explained about the related issue.
Furthermore, we cannot fix the façade light conduiting and wiring after fixing the aluminum because
we need to cut the block wall and the position of the points are very close to aluminum line as well we
hold the external plaster because of the façade lighting issue.
So, kindly clear this issue as you are willing to change the drawing and provide nominated
subcontractor to co-ordinate for MEP shop drawing and advice for aluminum work
Regards,
For xxx Contracting L.L.C.
xxx
Project Manager