Date: xxx
Ref: xxx
Kind Attn :Mr. xxx
Project :2B + G + 14 + Lower Roof Hotel Building on Plot No. xxx at Al Barsha
1st, Dubai U.A.E.
Subject : Intimation for the Work under hold between 11th to 12th floor vertical element due to over night rain , wind and electrical fault in tower crane
Dear Sir,
With reference to above, there was over night rain from thursday night to Saturday (16.02.17 -18.02.17) and there was a heavy wind and because of that we could not work yesterday (18.02.17) at floor no.11 for vertical element and note the following:
- Due to over night and morning rain, the tower crane affected due to moisture and we could not operate for entire day.
- Because of the heavy wind we could not work for any vertical elements due to non functionability of the crane and wind pressure.
So, this is for your kind intimation that interruption for the progress of slab work from 11th to 12th floor.
Regards,
For xxx Contracting L.L.C.
xxx
Project Manager